Data Center Cold Aisle Containment Curtains

Installation

Data Clean offers professional installation.

Curtain containment installation follows the same layout steps above:

  1. First, the DCT is installed with consideration given to obstructions.
  2. Once the DCT is in place, the hook bar is attached with or without fuse links and lanyards, as appropriate.
  3. The curtain panels are hung and secured in place with the hook bar cap.
  4. Finally, curtains are trimmed and secured, as needed.

While not complicated, isolation curtain installation requires skills typically possessed by electricians or other mechanical tradespeople:

  • Cutting metal at 90°, 45°, and possibly other angles
  • Drilling metal and other hand tool skills
  • Layout, measurement, and leveling
  • Installation instructions are generic and not developed for specific designs – ability to follow layout details is essential

Generally, all curtain containment installations follow the same set of tasks. The harder these tasks are because of higher ceiling height, mechanical obstructions or congestion, the more time-consuming the installation.

Temperature Measurements

For comparison, be sure to take temperature measurements before and after curtain installation.